1. Required Documents and Deadlines Overview
Last updated
Last updated
No. | Documents | Documents | Documents | Documents |
---|---|---|---|---|
● No. 7, 8, 9 and 12 documents are mandatory for exhibitors who set up their own decorations.
● The organizer will not issue the exhibitor an exhibitor badge if the above-required documents are not submitted and paid before the deadline.
● Certain documents will be submitted online in electronic form, which shall have the same validity as the original documents. This is hereby declared.
1
Official Promo Materials
Exhibitors' Site completion
2024/10/4
Late payment
is considered a waiver.
2
Steam Event
Exhibitors' Site completion
2024/10/15
Late payment
is considered a waiver.
3
G-EIGHT Trading Card Materials
Exhibitors' Site completion
2024/10/15
Late payment
is considered a waiver.
4
Additional Exhibitor Badge Application
Exhibitors' Site completion result: stamping and uploading
2024/10/15
Invoice stamps are required.
Late payment
is considered a waiver.
5
Tickets Bulk Purchase Application
Exhibitors' Site completion result: stamping and uploading
2024/10/15
Invoice stamps are required.
Late payment
is considered a waiver.
6
Special Work Uniforms and Large Props Application
Exhibitors' Site completion
2024/10/15
Late payment
is considered a waiver.
7
※Booth Design Layout
Exhibitors' Site completion
2024/10/15
2024/10/20 Organizer's reply
8
※Construction Safety and Health Regulations Affidavit(Attachment1)
Seal, and upload the results.
2024/10/20
Stamps are required.
9
※Interior Decoration Affidavit (Attachment2)
Seal, and upload the results.
2024/10/20
Stamps are required.
10
Key Visual Backdrop ※Submission is required for all organizers who decorate their booths.
Exhibitors' Site completion
2024/10/25
Late payment
is considered a waiver.
11
Advertising Design ※Applicants for advertising space must submit required materials.
Exhibitors' Site completion
2024/10/25
Late payment
is considered a waiver.
12
※Booth Water and Electricity Layout
Exhibitors' Site completion
2024/10/31
Invoice stamps are required.
Late payment
is considered a waiver.
13
Booth Power Supply Application
Exhibitors' Site completion result: stamping and uploading
2024/10/31
Invoice stamps are required.
Late payment
is considered a waiver.
14
Additional Equipment Application
G-EIGHT exhibitors' site completion Result: stamping and uploading
2024/10/31
Invoice stamps are required.
Late payment
is considered a waiver.
15
Unloading Dock Parking Application
Exhibitors' Site completion
2024/10/31
Late payment
is considered a waiver.
16
Special Vehicle Entry Application (Attachment5)
Seal, and upload the results.
2024/10/31
Stamps are required
17
Special Workwear and Large Prop Final Photos
Exhibitors' Site completion
2024/10/31
Late payment
is considered a waiver.
18
Press Release Outlets
Exhibitors' Site completion
2024/11/10
Late payment
is considered a waiver.
/
Live programs/stage programs *Required for invited and stage slot participants.
Individual contacts
2024/10/31
A
Air conditioning usage application during setup and teardown periods (Attachment6)
Complete on-site
Based on daily requirements
Late payment
is considered a waiver.
B
Overtime Application(Attachment7)
Complete on-site
Based on daily requirements
Late payment
is considered a waiver.
C
Additional Equipment Request Form (Attachment8)
Complete on-site
Based on daily requirements
Late payment
is considered a waiver.
D
Bump-in/Bump-out Inspection Form (Attachment9)
Complete on-site
Compliance with Evacuation Requirements
Mandatory field